Do I need a permit to repair or underpin a foundation in BC?
It depends on the council: Kamloops and Penticton need a permit to underpin foundation walls or repair structural parts, and Coquitlam needs none to repair drain tile.
Opens the lot's report at this answer. If an address isn't found, try the PID, the 9-digit parcel number on the land title or assessment notice.
What the answer means
No provincial rule says whether foundation work needs a building permit: each council's or regional district's building bylaw does. Of the councils we read, Kamloops and Penticton need a permit to dig a basement deeper for headroom or underpin foundation walls, and to install, change, remove or repair structural components, and Coquitlam needs one to repair a building's structural components but not to repair drain tile. Kamloops and Penticton add that work they otherwise exempt can still need a permit if it could compromise a structure or the property next door, or sits on geotechnically sensitive ground.
- Who decides
- Whether work needs a building permit is set by the local building bylaw, so the answer is the council's, or the regional district's where it runs building inspection (our reading; see building permits for which electoral areas have it). Where no one inspects, there is no permit to get, but the work is still the owner's to answer for (our reading).
- Kamloops
- The City of Kamloops lists among the interior renovations that will require a permit excavating a basement to increase existing headroom or underpinning foundation walls, and installing, changing, removing or repairing load-bearing walls and other structural components. It adds that minor work it lists as exempt may need a permit if it could structurally compromise a structure or adjacent property, or is proposed in an environmentally or geotechnically sensitive area such as a steep slope (its Bulletin No. 23-01, When Building Permits Are Required, revised April 2025).
- Penticton
- The City of Penticton's bulletin lists the same work as needing a permit, excavating a basement for headroom or underpinning foundation walls and installing, changing, removing or repairing structural components, with the same note on work that could compromise a neighbouring structure or sits on sensitive ground (its Bulletin No. 13-01, revised February 28, 2019).
- Coquitlam
- The City of Coquitlam needs a building permit for the restoration, maintenance or repair of a building's structural components and systems, and none for repairs that don't affect the structural or fire and life safety performance of a building, for emergency maintenance, or for repairing drain tile; it notes that work needing no permit must still meet its bylaws and the BC Building Code (its Building Division FAQ).
- After a flood or fire
- Kamloops and Penticton have the owner or restoration contractor arrange an inspection once the fire department or an engineer has finished its investigation, to decide whether the repairs need permits, and say they expedite those permits (their bulletins). See rebuilding after a flood.
- The engineer
- Underpinning, a new footing or a cracked wall that is moving carries the house's weight, so councils commonly ask for a structural or geotechnical engineer's design and field review before they issue the permit, and a home inspector who finds active movement will most often point you to one (our reading; see geotechnical reports). Ask the council what its permit needs for the work you plan.
- What cracks can mean
- Thin, dry shrinkage cracks in a concrete foundation are common; cracks that are wide, stepped, leaking, or wider at one end, and doors that stick or floors that slope, can mean the ground is moving and are worth an engineer's look (our reading). Water against the wall is the drains' job (see perimeter drains); a slope, fill or old mine workings under the lot are the ground's (see steep lots and old coal mines).
- Digging beside it
- Digging along or under a foundation can hit buried lines: a locate request before digging is free (see call before you dig). Kamloops and Penticton say digging near another building can need a permit even where the work would otherwise be exempt (their bulletins), and the neighbour's side is set out on construction next door.
- Earthquake work
- Anchoring the house to its foundation and bracing the short walls under the first floor is seismic strengthening, set out on seismic retrofits, and is structural work under the bylaws above (our reading).
- Before work starts
- Before work begins on renovating a building, every employer responsible for the work, and the owner, must have a qualified person inspect it for hazardous materials (Occupational Health and Safety Regulation s. 20.112), so hired work on an older foundation and the basement around it is work the survey reaches (our reading; see asbestos).
- What it means for a buyer
- Kamloops lists what starting work without a permit can lead to: a stop work order, remedial repairs and removal of materials, fines, doubled permit fees, and a notice on title that work was done without permits (its Bulletin No. 23-01). Foundation work done without a needed permit is the buyer's to deal with once the sale completes (our reading; see unpermitted work), so ask for the permit file and any engineer's letters before subjects come off.
Our summary of the City of Kamloops' Bulletin No. 23-01 (revised April 2025), the City of Penticton's Bulletin No. 13-01 (revised February 28, 2019) and the City of Coquitlam's Building Division FAQ, read 2026-10-28, and of the hazardous materials survey as its own page reads it. Other councils' building bylaws differ and we haven't read them: ask the council.
Source: Bulletin No. 23-01, When Building Permits Are Required, City of Kamloops (revised April 2025; summarised in our words, read 2026-10-28); Building Bulletin No. 13-01, When Are Permits Required?, City of Penticton (revised February 28, 2019; summarised in our words, read 2026-10-28); Building Division FAQ, City of Coquitlam (summarised in our words, read 2026-10-28); Occupational Health and Safety Regulation, Part 20 (s. 20.112), WorkSafeBC (summarised in our words, read 2026-10-19).
Before you buy: who to ask
- The seller or their agent
- Has the foundation been repaired, underpinned or dug deeper, when and by whom? Was there an engineer, and was a permit taken and closed? Has the basement ever leaked, and have the cracks grown?
- The local government
- Is there a building permit on file for past foundation work? Does your bylaw need a permit, and an engineer, for the work I plan?
- Your home inspector or a specialist
- Are the foundation cracks ones to watch or ones for an engineer? Do the floors slope, or the doors stick?
Look up the lot above: its buildable area section gives the slope, and its earthquake section the shaking the foundation has to stand up to.