The building code makes the builder shore, underpin or brace when digging may endanger a neighbouring building; the council's bylaws set permits and noise hours, and damage is a claim against the builder.

Opens the lot's report at this answer. If an address isn't found, try the PID, the 9-digit parcel number on the land title or assessment notice.

Share

TextEmail

Text and Email open your messages or email app with this message, ready to edit.

What the answer means

A house beside a lot being built on is protected first by the BC Building Code: the builder must keep the public safe and must shore, underpin or brace where digging may endanger a neighbouring building. The council's building and noise bylaws add the permit, the site plan and the hours. Damage to your house is a matter between you and whoever did the work.

Adjoining buildings
If excavating may endanger the stability of adjoining buildings, adequate underpinning, shoring and bracing must be provided to prevent damage to, or movement of, any part of the adjoining building and a hazard to the public (BC Building Code 2018, Division B, Article 8.2.2.2). Excavations must be kept reasonably clear of water (8.2.2.1). The code doesn't say how near a building must be, or who decides whether it may be endangered; that's the builder's and their engineer's call, checked by the council where it inspects (our reading).
The site and the public
Part 8 applies to fire safety and the protection of the public during the construction, alteration or demolition of every building, an unfinished or abandoned one included (Article 8.1.1.1 (2)), and precautions must be taken so no person is exposed to undue risk (8.1.2.2). Where the work may be a hazard to the public, a covered way protects a public way within 2 m unless the work is in a solid enclosure (8.2.1.1), and where the work is 2 m or more from a public way, a strongly built fence, boarding or barricade at least 1.8 m high stands between the site and the public way or the site's open sides, its gates locked when the site is unattended (8.2.1.3). A site left idle has its hazardous part fenced, or its openings within 3 m of the ground barricaded (8.2.1.5). Whether a fence must stand on the line with a neighbouring yard, rather than a street, the code doesn't say (our reading).
Streets, waste and demolition
Safe passage past the site is kept for people and vehicles, a sidewalk beside it kept clear or a temporary one provided, and damaged sidewalks and streets restored (Articles 8.2.3.1, 8.2.3.4). Waste may not fall freely from storey to storey and goes into containers or an enclosure that keeps it in and the public out (8.2.5.1 to 8.2.5.3). Demolition protects the public as the BC Fire Code's Section 5.6 sets out (8.1.1.3). Streets and traffic are normally controlled by authorities other than the building department, such as the police (Note A-8.1.2.1.(1)).
Which code
We read Part 8 in the BC Building Code 2018 as BC Publications posts it, free; the 2024 code that applies to permits applied for now isn't free to read there, so whether it changed these articles is unclear: ask the council's building department.
The council's permit, New Westminster as the example
New Westminster's Building Bylaw No. 6897 bars construction, demolition or excavation without a permit (s. 7.1.1), lets a building official issue an excavation permit before the building permit (s. 14.5), and asks for a surveyor's site plan showing all surface drainage and how surface water will not affect neighbouring properties (s. 11.1.4.8). The owner posts the permit where it can be seen (s. 17.3.1) and pays for damage to the City's works (s. 17.2). The bylaw says it doesn't protect owners from economic loss and that a permit or inspection is no warranty the work meets the code (ss. 3.2, 15.1), so the City's checks don't make it answer for damage to your house (our reading).
Noise hours, New Westminster as the example
Under New Westminster's Construction Noise Bylaw No. 6063, construction noise is allowed from 7:00 am to 8:00 pm Monday to Friday and from 9:00 am to 6:00 pm on Saturdays, and not on Sundays or statutory holidays; a resident may work on their own home on those days from 9:00 am to 6:00 pm if not for profit, quiet work is allowed at any time, and a builder who can't keep to the hours may apply for an exemption, as its 2026 bulletin says. Other councils set other hours, and a regional district has a noise bylaw only where it runs a noise service (see noisy neighbours).
Coming onto your lot
Entering land without the occupier's consent, other lawful authority or colour of right is an offence once it's fenced or posted or the occupier has said no (Trespass Act ss. 2, 3, as our trespass page reads it). We found no BC law giving a builder a right to work from, store on, swing a crane over or anchor shoring into the lot next door, so each needs your agreement, best in writing (our reading); whether a crane's swing over a lot is a trespass is unclear.
The ground under your house
At common law a landowner has a right to have their land supported by the land next door, so digging that lets it slip or subside can be a claim against whoever dug; how far that reaches to a building on the land, and when negligence must be shown, is for a court (our reading, with no plain-language BC source found).
Damage, dust and vibration
A neighbour can be liable in nuisance, an unreasonable interference with the use and enjoyment of your property; physical damage will usually meet the threshold, and the conduct can be intentional, negligent or without fault, as People's Law School states it for a damaged fence. A claim goes to the owner and the builder and their insurers, not the council (our reading); a small claim can go to the Civil Resolution Tribunal or the Provincial Court's Small Claims Court, each up to its own limit, and a court proceeding must generally start within 2 years of finding the damage (see defects after you buy for the limits).
Before the work starts
Photograph and date your foundation, walls, ceilings, driveway and fences, and ask the builder to survey your house before they dig or blast, so any crack can be told from one that was there (our reading). For blasting, some councils require that survey (see blasting). Lines and pipes under the ground are found through BC 1 Call before anyone digs (see calling before you dig).
What it means for a buyer
A vacant or older lot next door can be rebuilt, often to more homes than before (see small-scale housing). Ask the council for any open permits or applications on the lots beside you, and the seller whether building next door has cracked or flooded anything (our reading).

Our summary of the BC Building Code 2018, Division B, Part 8 (Sections 8.1 and 8.2 and Note A-8.1.2.1.(1)) as posted on BC Publications, the City of New Westminster's Building Bylaw No. 6897, 2003 (its consolidation to November 16, 2011; later amendments, if any, aren't in it) and its Construction Noise Bylaw information bulletin for 2026, and People's Law School's Q&A on a fence damaged by a neighbour (reviewed for legal accuracy in March 2021), read 2026-10-27; the Trespass Act and the claim routes as our trespass and defects pages read them (2026-10-21, 2026-10-26). Each council's bylaws differ, and whether you have a claim is a lawyer's question.

Sources (read 2026-10-27; summarised in our own words unless noted): BC Building Code 2018, Division B, Part 8, Section 8.1 (General), BC Publications; BC Building Code 2018, Division B, Part 8, Section 8.2 (Protection of the Public), BC Publications; BC Building Code 2018, Division B, Notes to Part 8, BC Publications; Building Bylaw No. 6897, 2003 (consolidated to November 16, 2011), City of New Westminster; Information Regarding Construction Noise Bylaw No. 6063, 1992 (2026), City of New Westminster; Our fence on the property line has been damaged by our neighbour, People's Law School.

Before you buy: who to ask

The local government
Are there open building, demolition or excavation permits, or development applications, on the lots beside this one? What construction noise hours apply here?
The seller or their agent
Has building or digging next door ever cracked the foundation, shifted a wall or sent water onto the lot, and was anything claimed or agreed?
Your home inspector or a specialist
Are there cracks or settlement now that a pre-construction survey should record?

Look up the lot above: its report gives the development applications near the lot where the council publishes them, who owns the land along the lot line and the slope across it.

See also blasting rock, noise from neighbours, encroachments, trespass, calling before you dig, retaining walls and a defect found after you buy.