PlaceDossier / Zoning / Sunshine Coast Regional District
Sunshine Coast Regional District Zoning Bylaw No. 722
The Sunshine Coast Regional District's zoning bylaw, which applies in Sunshine Coast, Electoral Area B, Sunshine Coast, Electoral Area F, Sunshine Coast, Electoral Area D, Sunshine Coast, Electoral Area E. Our summary of its 18 residential, rural, water, Industrial Nine (I9) and Park and Assembly Two (PA2) zones, from the bylaw as amended to September 10, 2026 and checked October 31, 2026. Its other zones aren't summarised here.
The zones side by side
| Zone | Homes allowed | Smallest lot for a subdivision | Lot coverage | Height limit |
|---|---|---|---|---|
| R1 Residential One | One house; with an auxiliary dwelling on a lot over 2,000 m²; two houses on a lot over 3,500 m² (s. 7.1.3). One secondary suite of up to 55 m² is allowed in each house (and on a lot where a duplex is the only home type listed), on top of the zone's count of homes (ss. 5.1.1 (h), 5.24); on SCRD sewer it needs the SCRD's sign-off on capacity before the building permit. | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 45% under 750 m², 35% from 750 m² (s. 7.1.4) | 11 m; a house on a lot under 750 m² 8.5 m unless the lot's average slope is over 20%; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11) |
| R2 Residential Two | One house; on a lot over 2,000 m², a house with an auxiliary dwelling; on a lot over 3,500 m², two houses, a duplex, or a house and a community care facility (s. 7.2). The density table also lists a duplex from 2,000 m² while the uses table says over 3,500 m², so a duplex between the two is unclear; ask the SCRD. One secondary suite of up to 55 m² is allowed in each house (and on a lot where a duplex is the only home type listed), on top of the zone's count of homes (ss. 5.1.1 (h), 5.24); on SCRD sewer it needs the SCRD's sign-off on capacity before the building permit. | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 35% under 3,500 m², 15% from 3,500 m² (s. 7.2.4) | 11 m; a house on a lot under 750 m² 8.5 m unless the lot's average slope is over 20%; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11) |
| R3 Residential Three | One house (s. 7.3.3). One secondary suite of up to 55 m² is allowed in each house (and on a lot where a duplex is the only home type listed), on top of the zone's count of homes (ss. 5.1.1 (h), 5.24); on SCRD sewer it needs the SCRD's sign-off on capacity before the building permit. | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 45% | 8.5 m (s. 7.3.7) |
| CR1 Country Residential One | One house; on a lot over 3,500 m², a house with an auxiliary dwelling; on a lot over 8,000 m², two houses, a duplex, or a house and a community care facility (s. 7.7). The density table also lists a duplex from 3,500 m² while the uses table says over 8,000 m², so a duplex between the two is unclear; ask the SCRD. One secondary suite of up to 55 m² is allowed in each house (and on a lot where a duplex is the only home type listed), on top of the zone's count of homes (ss. 5.1.1 (h), 5.24); on SCRD sewer it needs the SCRD's sign-off on capacity before the building permit. | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 35% up to 3,500 m², 15% above (s. 7.7.3) | 11 m; a house on a lot under 750 m² 8.5 m unless the lot's average slope is over 20%; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11) |
| CR2 Country Residential Two | One house (s. 7.8.4). One secondary suite of up to 55 m² is allowed in each house (and on a lot where a duplex is the only home type listed), on top of the zone's count of homes (ss. 5.1.1 (h), 5.24); on SCRD sewer it needs the SCRD's sign-off on capacity before the building permit. | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 35% up to 3,500 m², 15% above | 11 m; a house on a lot under 750 m² 8.5 m unless the lot's average slope is over 20%; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11) |
| RU1 Rural Residential One | In Areas B, D and E: one house under 3,500 m², a house and an auxiliary dwelling up to 8,000 m², two houses (or a house and a community care facility) above. In Area F: one house under 0.8 ha, a house and an auxiliary dwelling up to 1.75 ha, two houses above (s. 7.9.4 (a), (b)). Two named lots differ: one in Area F follows the Areas B, D and E table; on another, one house under 1.6 ha, two houses (or a house and a community care facility) from 1.6 ha (s. 7.9.4 (c), (d)). One secondary suite of up to 55 m² is allowed in each house (and on a lot where a duplex is the only home type listed), on top of the zone's count of homes (ss. 5.1.1 (h), 5.24); on SCRD sewer it needs the SCRD's sign-off on capacity before the building permit. | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 35% up to 3,500 m², 15% above | 11 m; a house on a lot under 750 m² 8.5 m unless the lot's average slope is over 20%; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11); a vehicle repair building 4.5 m, a manufacturing or storage building 6 m (s. 7.9.2) |
| RU1A Rural Residential One A | One house under 3,500 m², a house and an auxiliary dwelling up to 8,000 m², two houses (or a house and a community care facility) above (s. 7.10.4). One secondary suite of up to 55 m² is allowed in each house (and on a lot where a duplex is the only home type listed), on top of the zone's count of homes (ss. 5.1.1 (h), 5.24); on SCRD sewer it needs the SCRD's sign-off on capacity before the building permit. | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 35% up to 3,500 m², 15% above | 11 m; a house on a lot under 750 m² 8.5 m unless the lot's average slope is over 20%; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11); vehicle repair and manufacturing or storage buildings 6 m (s. 7.10.2) |
| RU2 Rural Residential Two | Area E: one house under 8,000 m², two houses (or a house and a community care facility) above. Areas B and D: one house under 1 ha, two houses up to 4 ha, three houses and an auxiliary dwelling of up to 55 m² above 4 ha. Area F: one house under 1.5 ha, two houses above (s. 7.11.4). One secondary suite of up to 55 m² is allowed in each house (and on a lot where a duplex is the only home type listed), on top of the zone's count of homes (ss. 5.1.1 (h), 5.24); on SCRD sewer it needs the SCRD's sign-off on capacity before the building permit. | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 35% up to 3,500 m², 15% above | 11 m; a house on a lot under 750 m² 8.5 m unless the lot's average slope is over 20%; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11); vehicle repair and manufacturing or storage buildings 6 m, a tourist information centre 4.5 m (s. 7.11.2) |
| RF1 Rural Forest One | One house (s. 7.12.2). One secondary suite of up to 55 m² is allowed in each house (and on a lot where a duplex is the only home type listed), on top of the zone's count of homes (ss. 5.1.1 (h), 5.24); on SCRD sewer it needs the SCRD's sign-off on capacity before the building permit. | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 5% (s. 7.12.3) | 11 m; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11; the 8.5 m house limit on small lots doesn't reach this zone) |
| RF2 Rural Forest Two | None: no house is allowed (s. 7.13.1) | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 5% (s. 7.13.3) | 11 m; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11; the 8.5 m house limit on small lots doesn't reach this zone) |
| RF3 Rural Forest Three | One house and one auxiliary dwelling, at most 355 m² of homes in all (s. 7.14.2) | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 15% up to 3.5 ha, 10% above (s. 7.14.3) | 11 m; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11; the 8.5 m house limit on small lots doesn't reach this zone) |
| RF4 Rural Forest Four | None: watershed protection, no house | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | Not set; buildings at most 100 m² in all (s. 7.15.3) | 11 m; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11; the 8.5 m house limit on small lots doesn't reach this zone) |
| RF5 Rural Forest Five | One house (s. 7.16.2). One secondary suite of up to 55 m² is allowed in each house (and on a lot where a duplex is the only home type listed), on top of the zone's count of homes (ss. 5.1.1 (h), 5.24); on SCRD sewer it needs the SCRD's sign-off on capacity before the building permit. | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 10% (s. 7.16.5); s. 7.16.3 also gives 15% up to 3.5 ha, so a lot under 3.5 ha is unclear; ask the SCRD | 11 m; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11; the 8.5 m house limit on small lots doesn't reach this zone) |
| AG Agricultural | One house of up to 350 m²; on a lot over 1 ha, an auxiliary dwelling of up to 90 m² too (s. 7.17.2). Everything here is also subject to the ALR Use Regulation (s. 7.17.2 (a)). One secondary suite of up to 55 m² is allowed in each house (and on a lot where a duplex is the only home type listed), on top of the zone's count of homes (ss. 5.1.1 (h), 5.24); on SCRD sewer it needs the SCRD's sign-off on capacity before the building permit. | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 15% for all buildings but greenhouses; 10% for the house and its buildings; 50% for greenhouses (s. 7.17.5) | 11 m; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11; the 8.5 m house limit on small lots doesn't reach this zone) |
| PA2 Park and Assembly Two | No house of its own: one single-unit dwelling to house a caretaker or watchman, as an auxiliary use (s. 12.2.2(c)). A secondary suite is allowed where a single-unit dwelling is (s. 5.1.1 (h)) but goes with a principal dwelling (s. 5.24.1), so whether the caretaker's home may have one is unclear: ask the SCRD | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 35% (s. 12.2.3) | 11 m; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11) |
| I9 Industrial Nine | No house of its own: one single-unit dwelling to house a caretaker or watchman, as an auxiliary use (s. 11.9.2(c)). A secondary suite goes with a principal dwelling (s. 5.24.1), so whether the caretaker's home may have one is unclear: ask the SCRD | Set by the lot's subdivision district, not its zone (s. 4.2): from 1,000 m² to 100 ha; a lot's report gives its district in "What you can build (zoning)", under "The record", as "Subdivision district (smallest new lot)" | 50% (s. 11.9.4) | 11 m; a detached auxiliary dwelling or accessory building 8.5 m (s. 5.11) |
Lake zones
These zone the water in front of shoreline lots: what a lot may have on it.
| Zone | On the water |
|---|---|
| W1 Water One | a dock for the upland lot of up to 65 m², a boathouse up to 35 m around, a free-standing float of up to 10 m², public boat ramps; no houseboats or marine ways; 4.5 m high at most (s. 10.2) |
| W2 Water Two | log booming and sorting, transfer and storage of forestry and industrial goods, boat ramp and moorage of working vessels; no aquaculture (s. 10.3) |
"Not set" means the zone itself sets no figure; general rules elsewhere in the bylaw may still apply. Each zone's page has its uses, setbacks and the general rules that apply to it.
Where the bylaw is unclear
Points the bylaw's text leaves unclear. Ask the SCRD's planning department before you rely on them.
- R1, R2, CR1, RU1, RU1A, RU2, RF3: An auxiliary dwelling, attached or detached, is up to 90 m² of floor area (55 m² where more than two houses are allowed), enclosed parking not counted (s. 5.2). Section 5.24.4 says auxiliary dwellings, like suites, aren't counted in a lot's most homes, while the zone's density table counts one as a home; how the two read together is unclear, ask the SCRD.
- R1, R2, CR1, CR2, RU1, RU1A, RU2, PA2: Livestock only on a lot over 3,500 m² (s. 5.6 sets 3,500 m² as the minimum), with pens, troughs and feed, bedding or manure storage 20 m from lot lines, and the premises registered with the Province (s. 5.6). The bylaw's livestock may include poultry and bees (Part 13), which s. 5.5 allows on smaller lots with its own setbacks; which rule a small flock follows is unclear, ask the SCRD.
- R3: Poultry, rabbits and bees: R3 doesn't list residential agriculture, while s. 5.5.1's table covers every zone but AG and the multi-family zones, so whether a lot here may keep them is unclear; ask the SCRD.
- RU2: Cannabis production: the zone's table says a lot over 8 ha (s. 7.11.2), while s. 5.9.1 allows standard cultivation in RU2 on a lot of not less than 8 ha and micro cultivation or a nursery from 4 ha, so a lot of exactly 8 ha and a micro grower between 4 and 8 ha are unclear; ask the SCRD. Outside the ALR, standard cultivation 30 m and micro cultivation or a nursery 15 m from lot lines; never as a home business (ss. 5.9.2, 5.9.4).
- I9: The zone lists an automobile wrecking and storage yard (s. 11.9.2), while s. 5.19.1 bars wrecking vehicles and storing junk outside on any lot but in I7; how the two read together is unclear, ask the SCRD.
Site-specific exceptions listed in the bylaw by legal description can add or change uses for one property, and development permit areas, the ALR and building rules apply on top. Confirm with the SCRD's planning department before you buy or build.
Source: Sunshine Coast Regional District Zoning Bylaw No. 722 (summarised in our words); zone map: Open Government Licence – Sunshine Coast Regional District.