What is a Type 1, Type 2 or Type 3 septic system in BC, and what is a mound?

The type says how clean the water leaving the tank is: Type 1 is a septic tank only, Types 2 and 3 treat it further; a mound is a raised sand field it soaks into.

Opens the lot's report at this answer. If an address isn't found, try the PID, the 9-digit parcel number on the land title or assessment notice.

Share

TextEmail

Text and Email open your messages or email app with this message, ready to edit.

What the answer means

A BC septic system has two parts: a treatment method, which BC's Sewerage System Regulation classes as Type 1, 2 or 3 by how clean its effluent is, and a discharge area, the field the effluent soaks into, which the Standard Practice Manual builds as trenches, beds, mounds and other kinds. The soil and slope of the lot decide which mix will work.

Two parts
A sewerage system treats domestic sewage with one or more treatment methods and a discharge area that receives the effluent (Sewerage System Regulation s. 1). The manual adds that the field also treats the effluent, but its main job is to disperse it (Standard Practice Manual II-4.2).
Type 1
Treatment by septic tank only (s. 1, "treatment method" (a)); the manual's standard is a septic tank with an effluent filter (II-4.2.1). Solids settle in the tank and the liquid flows on to the field.
Type 2
Treatment producing an effluent that consistently holds less than 45 mg/L of total suspended solids, with a 5-day biochemical oxygen demand under 45 mg/L (s. 1, "treatment method" (b)). The manual calls the usual unit a packaged treatment plant, a pre-built aerobic treatment unit (glossary).
Type 3
Treatment producing an effluent under 10 mg/L of total suspended solids, a 5-day biochemical oxygen demand under 10 mg/L and a median fecal coliform density under 400 colony forming units per 100 mL (s. 1, "treatment method" (c)). Unless a professional supervises, no one may build or maintain one (s. 6 (3) (a)).
Who builds and keeps them
A Type 1 or Type 2 system is built and maintained only by an authorized person, a registered onsite wastewater practitioner or a professional, or by the owner on their own land under one's supervision (s. 6 (1)). The practitioners' registration covers Type 1 and Type 2 only (ss. 1, 7), and any system designed for more than 9,100 litres a day also needs a professional (s. 6 (3) (b)).
Why cleaner effluent
The soil can take cleaner effluent faster, so the field can be smaller: in sand or loamy sand of favourable structure the manual allows 30 litres a day per square metre of Type 1 effluent, 60 of Type 2 and 90 of Type 3 (Table II-22). It names a small dispersal area or shallow soil as the reason to choose Type 2 or 3, and higher maintenance, a need for power and special measures for seasonal use as the cost (Table III-6).
Kinds of field
The manual's dispersal systems are trenches, seepage beds, shallow, at-grade and raised systems, at-grade beds, the Alberta At Grade system, sand mounds and sand-lined trenches and beds, subsurface drip dispersal, combined treatment and dispersal systems, evapotranspiration beds and BC zero discharge lagoons, fed by gravity or by a pump dosing it under pressure (II-6).
Where each fits
Trenches aren't allowed on slopes over 45%, or over 25% with less than 90 cm of soil above the limiting layer; raised systems, sand mounds and at-grade beds not over 25%; seepage beds and trickling gravity not over 15% (Tables II-5, II-6). An Alberta At Grade system takes only Type 2 or 3 effluent on a forested site, and a BC zero discharge lagoon needs a property of at least 1.6 ha and a slope of 12% or less (Table II-6).
A mound
A sand mound is a field built up in sand over the native soil, used where there is little unsaturated soil above rock, hardpan or the water table, or where the soil drains very fast or very slowly; it isn't allowed on slopes over 25%, is dosed under pressure on a timer, and has, in the manual's words, a high site impact (Table III-6). No sand mound may be built in the 1-in-20-year floodplain (II-4.1.5).
Upkeep by type
For the first 12 to 14 months the manual's minimum visits are at 12 months for Type 1, every 6 months with effluent tests for Type 2, and at 1, 7 and 13 months with fecal coliform tests for Type 3. After that the maintenance plan sets the schedule, at least every 2 years for Type 2 or 3 and every 5 years for others (II-7.1, Table II-62).
Cottages and seasonal homes
The manual warns that Type 2 or 3 systems may not suit some seasonal dwellings, such as a vacation cottage, because they usually run on electricity and rely on biological processes that intermittent use can't sustain (III-2.2.1).
What a listing's words tell you
"Type 2" or "mound" says what was built, not that it was filed, certified or still working. The filing with the health authority, the letter of certification and the maintenance plan an authorized person gives the owner show what was approved (s. 9), and an inspection shows its state (our reading; see a septic inspection).
What a report shows
A report screens the room on the lot for a field against the recorded wells, mapped water and the lot line, and the slope, and says where a community sewer is mapped. Which system a lot has isn't open data, so it can't say.

Our summary of the Sewerage System Regulation (B.C. Reg. 326/2004, ss. 1, 6, 7, 9) on BC Laws and the Sewerage System Standard Practice Manual, version 3 (September 2014: II-4.1.2, II-4.1.5, II-4.2, II-5.5, II-6, II-7.1, III-2.2.1, III-4.1.2), read 2026-10-25. We name no installer, product or price; which system suits a lot turns on its soil, which only a site assessment shows.

Sources (read 2026-10-25; summarised in our own words unless noted): Sewerage System Regulation, B.C. Reg. 326/2004; Sewerage System Standard Practice Manual, version 3 (2014), Province of BC (II-4.1.2, II-4.1.5, II-4.2, II-5.5, II-6, II-7.1; III-2.2.1, III-4.1.2); Registrant directory (pick ROWP), ASTTBC (read 2026-10-25).

Who to ask

The seller or their agent
Which type of system is it and what kind of field, when was it built, and can I have the filing, the letter of certification, the maintenance plan and the service records?
A registered onsite wastewater practitioner
Is the system working as its type should, what does its maintenance plan ask for, and would it take more flow if we add bedrooms or a suite?
The regional health authority
What is on file for this system, and was it certified?

Look up the lot above: its report screens the room for a septic field against the wells, water, lot line and slope, and says where a community sewer is mapped.

See also room for a septic field, a septic inspection before you buy, septic maintenance, adding a suite or bedrooms on septic, holding tanks, greywater systems, perc tests and steep lots.

Buying rural land? Before you buy rural land in BC: the nine questions that decide an offer, on one printable page.